Supplier development								
				Customer:
									TIER 1 plastic parts supplier 								
				Location:
									Spain								
				
															Target:
									Ensure quality and quantity of parts during new launch phase 								
				Tasks:
									Interim Managent. Support in improving operations of the 2 supplier plants during new models launch phase 								
				Project Key Figures:
									18 months duration
4 Quality Engineers
1 Logistic Engineer
3 mould specialists
3 maintenance technicians
				4 Quality Engineers
1 Logistic Engineer
3 mould specialists
3 maintenance technicians
Achievements:
									Improvement of 30% in Plant OEE. Reduction of scrap rate. Ensuring quality and quantity during overall launch phase.